North Pier Pontoons - Breakwater repairs update

Oban North Pier Pontoons were damaged during Storm Eowyn in January 2025. Following detailed investigation, some parts of the facility remained closed, for public safety, when it re-opened in March 2025. Further work is now underway to re-open as much of the facility as possible for the season starting April 2026.

Oban North Pier Pontoons were damaged during Storm Eowyn in January 2025. Following detailed investigation, some parts of the facility remained closed, for public safety, when it re-opened in March 2025. Further work is now underway to re-open as much of the facility as possible for the season starting April 2026.

Update: 20 March 2026

This week has seen another strong spell of progress on the breakwater repairs, with the contractor working extremely hard to move the project forward and complete as early as possible.

Leg 2 of the breakwater has now been fully installed onto its moorings and the bridge linking Leg 1 and Leg 2 returned to position, marking a major milestone in the repair programme. In addition, the access bridge that was recovered from the seabed earlier has now been fully checked and approved for re-use following some minor welding repairs to the handrails. We are currently awaiting delivery of a new hinge bracket, after which the bridge can be put back in place between Leg 2 and Leg 3.

Work has also continued on Leg 3, where the team has partially reinstated the units and is now focusing on securing the most damaged section to the end of the breakwater. 

Some further tasks will still be required on the breakwaters, including installing the third bridge, repairing fenders, and reinstating water and electrical services. Because of this, the facility will reopen on a phased basis.

As covered in last week’s update, we expect Leg 3 to open under a weight restriction as part of its temporary configuration. Details on this will be confirmed in due course as we move steadily to reopen the facility to all. 

Image
The Grace Lamont moving the damaged unit to the end of the facility

The Grace Lamont moving the damaged unit to the end of the facility

Update: 13 March 2026

Despite some very challenging weather this week, the team made excellent progress on the breakwater repairs. One of the most important stages of the project, re‑tensioning the breakwaters, has now been completed. This involved carefully installing new cabling inside the units and pulling them to a high level of tension before securing them in place. The team worked hard through some difficult weather conditions to complete this stage.

During the recovery of the access bridge, some cracks were discovered in the aluminium handrails. As a precaution, the bridge has been taken to the fabricator’s yard to be fully inspected, repaired and cleaned. It will return to site once it’s ready for reinstallation.

Today (Friday 13 March), the team have begun to move the breakwater units back into their original positions and reconnecting them to the mooring chains. This will let us monitor how the units behave in their new configuration and check whether any final adjustments to the cable tensioning are required before we seal everything off.

There are still works to complete, but this week marks a very positive step forward and we hope to be in a position to share a clearer timescale for reopening soon.

As part of the preparation for a safe reopening, the most damaged unit is being moved to the end of the facility. Although it won’t be available for berthing, it will still play an important role in providing protection and supporting safe navigation. To do this, it will be securely connected to the neighbouring unit using approved temporary fittings, allowing it to act as a buffer helping vessels to enter the facility safely.

Image
the most damaged part has be recovered to the pier ready for removal

The most damaged part has been recovered to the pier ready for removal.

Because this leg of the breakwater will be operating in a temporary configuration until the replacement unit is installed, we expect to put a weight limit in place for vessels using Leg 3. This is a precautionary measure while we observe how the units behave in their new arrangement. Details of the weight limit will be confirmed before reopening.

Image
The CT Barnston and team starting to move Leg 3 back into position

The CT Barnston and team starting to move Leg 3 back into position

Although this means Leg 3 won’t be fully operational straight away, the temporary solution ensures the breakwater will still offer protection, safe access, and continued functionality for the wider facility. This forms part of our plan to get the North Pier Pontoons reopened as soon as it is safe to do so, while still progressing towards the long‑term repairs.

Update: 5 March 2026

Over the past fortnight, Shearwater’s marine team have completed one of the most carefully planned stages of the project, assessing and then cutting the tension cables that hold the breakwater units together. Cutting the tension cables is a highly specialised and potentially hazardous operation. After detailed preparation and safety checks, the cables were successfully cut on Tuesday 3 March, which means each breakwater unit is now fully separated and can be worked on individually.

Image
Exposed tension anchors

Exposed tension anchors - the ends of the tension anchors being prepared for removal

With the units now free, Shearwater can begin repositioning them and carrying out targeted repairs on those that suffered the greatest storm damage.

Image
recovering cables

Recovering cables - The team at work recovering the cables onto the units for inspection and then disposal

Next week

The site team will move on to a series of minor but important repairs on the units, including:

  • localised concrete repairs
  • replacement of damaged mooring chain links
  • Repairing damaged to fendering and some bent pedestals, these were not affected by the storm but we are using this opportunity to carry out these repairs whilst the facility is closed, and
  • assessing the recovered bridge to certify the welds are still intact and the alignment remains true, hopefully allowing us to re-use this asset.

These works will allow the units to be re‑arranged and then re‑tensioned once repairs are complete.

 19 February 2026

Shearwater have made steady progress on site this week.

The CT Barnston multi‑purpose vessel joined the team at the end of last week, bringing significant heavy lifting capability that is vital to supporting these operations. Its arrival has already made a huge difference to the recovery and repair work.

Bridge Recovered 

On Monday, the team successfully recovered the bridge section that was swept away during the January 2025 storm. Despite spending a full year underwater, the bridge has emerged in surprisingly good condition.

Over the coming days it will be thoroughly cleaned and inspected, including checks to its welds and fixings, to confirm whether it can be safely reinstated as part of the final repair works.

Image
Recovered Bridge -the lost bridge on the pier ready for inspection

Recovered Bridge -  the lost bridge on the pier ready for inspection

Mooring Chains Lifted

Tuesday and Wednesday saw the team focused on the heavy mooring chains that connect each breakwater unit. Using the lifting gear aboard the CT Barnston, the crew worked carefully to raise each chain and detach it whilst trying to avoid further damage to the units. Each chain weights around two tonnes and needed to be carefully lifted, detached from the unit, attached to a mooring buoy and gently replaced into the water. They also needed to carefully sequence the work around the units to ensure the chains didn't become entangled or caused any undue twisting to the units.

Their careful approach paid off and by the middle of the week, they had successfully freed the units and were able to remove Breakwaters 2 and 3, relocating them safely inside the shelter provided by Breakwater 1. This creates a more controlled environment for the next stages of the repair programme.

Image
Breakwaters 2 and 3alongside - Both breakwaters safely relocated and ready to be separated

Breakwaters 2 and 3 alongside - both breakwaters safely relocated and ready to be separated

This stage of the project had originally been expected to take three days per unit, but thanks to the team’s hard work and efficient planning, both units were completed in just two days. This strong progress is a key reason why the decision was made to carry out this work now, rather than before the Christmas break when weather and daylight would have made operations much more difficult.

Mooring Chains Tidy

The team of divers spent Thursday cleaning and inspecting the mooring chains and ensuring they were tidy in preparation for when the breakwaters are re-attached. Some defects have been found that were general wear and tear and not specifically caused by the storm. These defects in the links will be replaced as part of this work.

We will continue to provide updates as the work progresses.

Update – 13 February 2026

Shearwater Marine Services Ltd commenced work on site on Monday to begin carrying out the temporary repairs.

This work will include relocating the damaged sections in the facility to maximise the usable berthing area, building on the limited opening in 2025. In parallel, design work for permanent replacement units is underway.

Image
looking towards the North Pier, showing the most damaged unit, with Oban in the background

Looking towards the North Pier, showing the most damaged unit, with Oban in the background.

Working from their support vessel, the Grace Lamont, Shearwater’s dive team has started by inspecting the underwater condition of the breakwater units and their mooring chains before beginning the careful process of detaching and repositioning them. Further updates will be provided as the work continues over the coming weeks.

Image
the Grace Lamont alongside the damaged breakwater - with the Island of Kerrera in the background

The Grace Lamont alongside the damaged breakwater - with the Island of Kerrera in the background.

What is being done

A key priority of 51³Ô¹ÏÃâ·ÑApp and Bute Council is to re-open as much of the facility as possible from April of 2026 and to ensure Oban can welcome the returning Clipper Race participants in July 2026.

The recommended approach to meet these deadlines involves relocating damaged units from the middle of Breakwater 2 to the outermost section of Breakwater 3. This configuration is expected to increase available berthing by allowing the second section to reopen, and increase the berthing capacity by 160 metres. Permanent replacement units would then be designed over the summer and installed over the following winter period of 2026/27.

The working being carried out this Spring will involve uncoupling breakwater units, repositioning them and re-tensioning the system. It is not yet known if the third section of breakwater will be re-opened, this will depend on whether successful re-tensioning can be achieved given the damage and confirmation will be provided as the works continue.

Safety remains the Council's priority, and we thank users and the community for their continued patience while these works are carried out. Further updates will be shared as the works progress.

What happened

The North Pier pontoons are an important part of Oban’s waterfront, offering valuable access for local users, visiting vessels, and the wider marine community. Over the past year, they have been affected by significant weather‑related damage. On 24 January 2025, Storm Eowyn caused significant damage to the facility, including visible damage to the pontoons and breakwater sections that protect the inner berthing area. As a safety precaution, the facility was initially closed completely to allow comprehensive above and underwater inspections.

A detailed dive survey examined the mooring chains, anchor blocks and underside of the units to assess the overall integrity of the pontoon system. Initial repair work was undertaken to some fixing points, and several damaged pontoons floats were replaced allowing the inner finger pontoons to reopen safely in March 2025.

Additionally, divers confirmed the first section of breakwater, which provides approximately 200m of berthing area, was sound and could be re-opened for use by larger vessels.

However, due to the damage encountered, the remainder needed to stay closed for safety reasons.

To plan the necessary long‑term repairs, specialist consultant engineers reviewed the dive report findings along with earlier investigations into cracking that had been seen on some units prior to the storm. They developed a range of repair and replacement options, each with corresponding timescales.